Energy efficiency improvement under reconstruction of Oxygen shop and steel continuous casting section of Blast Oxygen Furnace shop #2 at OJSC “Novolipetsk Steel”

The project activity consists of the improvement of the energy efficiency by the implementation of two subprojects. The subprojects are implemented at OJSC “Novolipetsk Steel”. The names of subprojects are presented below:

  1. Construction of new air separation plants at the Oxygen shop;
  2. Reconstruction of two continues casting machines No 6 and 7 at the Basic Oxygen Furnace shop No 2.

Implementation of subproject 1 enables to reduce electricity consumption significantly and subproject 2 – waste of steel and, respectively, fuel for steel production.

Project owner: OJSC “Novolipetsk Steel”

Location: Lipetsk, Lipetsk region

PDD volume of reductions: 1 089 061 tons CO2eq.

Track: 1

State of the project development: Determination and verification of the first monitoring report