Shaturskaya TPP is the third largest plant of the generating company OJSC “OGK-4”. A CCGT unit with an electrical capacity of 400 MW was installed and commissioned in mid-October 2010. The efficiency of new energy unit is around 56%, and it is fueled by natural gas.
The project is the first in Russia submitted to JISC for final registration according to Track 2 procedures.
Project owner: OJSC “OGK-4” (now – OJSC “E-on Russia”)
Location: Shatura, Moscow region
PDD Reduction Volume: 1 128 925 tons CO2eq.
Track: from 2 to 1
Project Status: First verification (for 2010) is finished
Link to JISC website may be found here