The JI project at Volyn-Cement, cement factory in
Global Carbon is developing all documentation for this project including an approach to set the baseline and monitoring plan.
The project at Volyn-Cement factory consist of the following:
- it is foreseen to increase to some 15 per cent the addition of non-carbonated raw material in the raw meal fed to the kilns;
- switch the technology of cement production from a wet process to a semi-dry production process will further decrease the emissions from fossil fuel combustion.
Emission Reductions
The total expected emissions reductions are around 1,207,508 tonnes of CO2e.
JI Project status
The Project Design Document of Volyn-Cement JI project was published at the JI UNFCCC website here.