Horlivka coke plant, Ukraine 2008


The JI project is planning to be implemented at Horlivka Coke Plant (HCP) owned by ISTEK LLC. The main product of the HCP is metallurgical coke. HCP is one of the oldest coke plants in Ukraine. It was put into operation in 1928 with two coke batteries. Global Carbon is developing all documentation for this project including an approach to set the baseline and estimate the emissions reductions.

The JI project at HCP includes installation of:

  • a steam boiler;
  • and steam turbo generator with all necessary auxiliary equipment.

The steam boiler will be able to generate 85 tonnes of steam per hour. The steam turbo generator will have a capacity of 12.5 MWe. The CHP will be fuelled by COG available for energy production – namely flared and used in the existing boiler house at the moment. The existing boiler house will be switch to stand-by mode and used during maintenance of the proposed CHP.

Emission Reductions

The total expected emissions reductions are around 174,948 tonnes of CO2e.